| Project Analysis | ||||||||||||||||
| Tasks | Date Started | Date Completed | Assigned to | % Complete | 24-Aug | 26-Aug | 28-Aug | 30-Aug | 1-Sep | 3-Sep | 5-Sep | 7-Sep | 9-Sep | 11-Sep | 13-Sep | 14-Sep |
| Planning | 24-Aug | 14-Sep | All | 100% | ||||||||||||
| Problem Definition | 24-Aug | 28-Aug | All | 100% | ||||||||||||
| Questions | 28-Aug | 1-Sep | All | 100% | ||||||||||||
| Narrowing | 1-Sep | 3-Sep | All | 100% | ||||||||||||
| Thesis | 3-Sep | 3-Sep | All | 100% | ||||||||||||
| Research Industrial Age | 28-Aug | 5-Sep | Andrew, Chris | 100% | ||||||||||||
| Research Information Age | 28-Aug | 5-Sep | Adam, Andy | 100% | ||||||||||||
| Research CWA | 28-Aug | 5-Sep | Mike, Ben | 100% | ||||||||||||
| Research Outside Topics | 28-Aug | 5-Sep | All | 100% | ||||||||||||
| Forming Report | 5-Sep | 5-Sep | All | 100% | ||||||||||||
| Writing Report | 5-Sep | 9-Sep | Mike, Ben | 100% | ||||||||||||
| Spreadsheet | 9-Sep | 9-Sep | Ben | 100% | ||||||||||||
| Uploading Report to Web | 12-Sep | 14-Sep | All | 100% | ||||||||||||
| Proofreading/Editing | 9-Sep | 12-Sep | Adam, Andy, Andrew, Chris | 100% | ||||||||||||
| Powerpoint Presentation | 10-Sep | 13-Sep | Adam, Andy, Andrew, Chris | 100% | ||||||||||||
| Forming Presentation | 9-Sep | 12-Sep | All | 100% | ||||||||||||
| Other Visual Aids | 9-Sep | 12-Sep | All | 100% | ||||||||||||
| Delivery of Presentation | 14-Sep | 14-Sep | All | 100% | ||||||||||||
| Analysis of Presentation | 14-Sep | 14-Sep | All | 100% | ||||||||||||
| Gant Chart | 24-Aug | 14-Sep | Andrew, Adam | 100% |